Contract documents for a construction contract will typically consist of:
- Contract drawings.
- Priced bill of quantities.
- Articles of agreement.
- Contract conditions.
- For contracts where there is a contractor’s designed portion: employer’s requirements, contractor’s proposals and contract sum analysis.
The ‘articles of agreement’ set out the core obligations of the parties involved. Typically, they consist of four sections:
- Recitals.
- Articles.
- Contract Particulars.
- Attestation.
By way of an example, the contents of the articles of agreement in the JCT Standard Building Contract (SBC) are set out below in more detail.
[edit] Recitals
Recitals contextualise the agreement, giving factual explanations for the basis of the contract. Seven recitals describe what is required and the events that have taken place.
[edit] First recital
Describes the work required by the employer, identifies the site, confirms the preparation of the design and bill of quantities.
[edit] Second recital
Confirms that a priced copy of the bill of quantities has been supplied by the contractor to the employer, with a priced activity schedule where required.
[edit] Third recital
Identifies the contract drawings.
[edit] Fourth recital
Identifies whether the employer is to be considered a contractor for tax deduction purposes under the Construction Industry Scheme.
[edit] Fifth recital
Refers to an information release schedule provided to the contractor by the employer (this is optional).
[edit] Sixth recital
Clarifies whether the works are to be carried out in sections.
[edit] Seventh recital
This only applies (along with three more recitals), where the contractor is obliged to complete design works under the provisions for a contractor’s designed portion.
[edit] Articles
These set out what is agreed between the parties.
[edit] Article 1
The obligation of the contractor, i.e. undertaking and completing the works subject to the contract documents.
[edit] Article 2
The obligation of the employer, i.e. to pay the contract sum or such other sum as becomes payable under the contract (through variations and/or correction of errors).
[edit] Article 3
Identifies the architect (or contract administrator) under the contract, and provides the employer with the power to maintain someone in the role of duty-holder (or employer’s agent).
[edit] Article 4
Identifies the quantity surveyor.
[edit] Article 5
Identifies the principal designer.
[edit] Article 6
Identifies the principal contractor.
[edit] Article 7
Makes reference to the right to adjudication in the event of any dispute.
[edit] Article 8
Makes reference to the right to arbitration in the event of any dispute.
[edit] Contract particulars
This section sets out the aspects of the contract that are particular to the project to which the contract relates. It is a schedule for the variables in the agreement and conditions. It is important that the variables are compatible with the relevant operating mechanism in the agreement, conditions and schedules as disputes may arise when either party applies the contract particulars information without proper reference to the operating clause.
Read more about contract particulars here.
[edit] Attestation
The attestation is the process of confirming that something is correct or genuine, or that a particular requirement has been met. It may be completed:
[edit] Under seal
Signed by both parties, witnessed and made clear that it is executed as a deed.
[edit] Under hand
A ‘simple contract’ that is signed just by the parties.
[edit] Related articles on Designing Buildings Wiki
- Agreement.
- Attestation in construction.
- Construction contracts.
- Contract conditions.
- Contract documents.
- Contract execution.
- Contract negotiation.
- Contracts under seal v under hand.
- Essentials of a contract.
- FIDIC.
- Intermediate Building Contract.
- Joint Contracts Tribunal.
- Named specialist work.
- NEC3.
- Period for reply.
- Procurement route.
- Sub-contract.
- Z clauses.
[edit] External references
- ‘The JCT 05 Standard Building Contract’ (2nd ed.), NDEKUGRI, I., RYCROFT, M., Butterworth-Heinemann (2009)
Featured articles and news
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Drone data at the edge: three steps to better AI insights
Offering greater accuracy and quicker access to insights.
From fit-out to higher-risk buildings.
Heritage conservation in Calgary
The triple bottom line.
College of West Anglia apprentice wins SkillELECTRIC gold.
Scottish government launch delivery plan
To strengthen planning and tackle the housing emergency.
How people react in ways which tend to restore their comfort.
Comfort is a crucial missing piece of the puzzle.
ECA launches Recharging Electrical Skills Charter in Wales
Best solutions for the industry and electrical skills in Wales.
New homebuilding skills hub launch and industry response
Working with CITB and NHBC to launch fast track training.